Basement Project Week 8, Days 1 & 2

Yesterday two of the three window sills were installed as will as the riser trim on the stairs. Today the painters were here all day.

Yesterday two of the three window sills were installed as will as the riser trim on the stairs. Because of the concrete wall, insulation, air gap, and then the new walls, our windows are quite deep. Nat is using some thick pine for a sturdy sill.

A photo of one of the windows with the newly installed sill.

The painters were here all day today. Looks like they got the ceiling painted and a first rough pass on the walls.

A photo of the newly painted ceiling. It is a charcoal color. The exposed duct work is painted the same color.