Landscape project week 5 day 5: another late day of working for the landscapers. They didn’t leave until after dark (hence the nighttime photo), but they got the bulk of the pavers laid, the wall caps in place, and filled in behind the wall.
Landscape project week 5 day 4: the landscapers started early and worked late today to get things in a good place before the rain starts. The drainage is installed to a point where work won’t get washed out (including some steps!), and the groundwork laid for the patio pavers.
Landscape project week 5 day 3: getting the drainage and side steps started.
Landscape project week 5 day 2: grading in preparation for pavers around the sun porch and demolition of the side steps.
Landscape project week 4 day 3: lots of progress on the wall and steps and backfilling behind it.